1. What possible paths from the start of the project until the end are there in this PERT chart? 2. Calculate the lengths of the paths. 3. Which path is longest? What is this path called? 4. How much slack does task J have? 5. If task P ran 2 days over time, what effect would this have on the finishing date of the project? 6. How many predecessors does task N have? 7. Is task E dependent on any tasks? |
|
|